| Sl.No |
Taluk |
Village |
Project Name |
Sanctioned Amount
(in Rs) |
Amount Spent (in Rs) |
Status |
| 1 |
Palacode |
Panchapally |
Providing New Borewell and Mini Power Pump and laying of PVC Pipe line in Sorakuruchi Village – Panchapally Village |
400000 |
399970 |
Completed |
| 2 |
Karimangalam |
Boomandahalli |
Laying of PVC Pipe Line From New Borewell to OHT in Mothur Village- Boomandahalli Village |
170000 |
168611 |
Completed |
| 3 |
Karimangalam |
Kalapanahalli |
Providing New Borewell and mini Power Pump (Near Crusher Unit) in Kalapanahalli Village |
210000 |
209818 |
Completed |
| 4 |
Karimangalam |
Kalapanahalli |
Providing New Borewell and Mini Power Pump near Kuppangarai Kattukottai Thar Plant. – Kalapanahalli Village |
200000 |
199774 |
Completed |
| 5 |
Palacode |
P.Chettihalli |
New G.I. Street Pipe Line Erection at Jothihalli Village H/o. P.Chettihalli Panchayat |
491000 |
490945 |
Completed |
| 6 |
Palacode |
P.Chettihalli |
New G.I. street pipeline erectin at Purathur Colony H/o. p.Chettihalli Panchayat |
211000 |
186341 |
Completed |
| 7 |
Palacode |
Jerthalav |
New G.I Pipe line erectrion from Borewell at Kavapatty Pirivu Road to Thimmampatty 30,000 litre OHT. H/o. Jerthalav Panchayat – Jerthalav Village |
625000 |
623921 |
Completed |
| 8 |
Karimangalam |
Kalapanahalli |
Extension of Pipe Line from Kalapanahalli OHT to Mel Theru H/o. Kalapanahalli – Kalapanahalli Village |
113000 |
0 |
Cancelled |
| 9 |
Karimangalam |
Kalapanahalli |
Erection of New Borewell with Minipower Pump with 1000 Lt hDP Tank at Mel Jiitikan Kottai H/o. Kalapanahalli Village |
246000 |
0 |
Cancelled |
| 10 |
Palacode |
Erraseegalahalli |
Extension of Pipe Line from Jumbermadu OHT to Krishnan and Mini House H/o. Erraseeglahalli |
55000 |
0 |
Cancelled |
| 11 |
Palacode |
Erraseegalahalli |
Erection of New Borewell, motor with pipeline, extention at Jumber Madu OHT H/o Errasegalahalli |
389000 |
0 |
Cancelled |
| 12 |
Nallampalli |
Indur |
Erection of New Borewell with Mini Power Pump near Paraikottai / Madhappan Kottai – Indur Village |
200000 |
199792 |
completed |
| 13 |
Nallampalli |
Indur |
Erection of New Borewell Motor with Motor Room and Pipe Line laying work at 60000 Lt OHT at Old Indur Village – Indur Village |
400000 |
392122 |
completed |
| 14 |
Nallampalli |
Indur |
Erection of New Borewell with Mini Power Pump at Indur PH centre – Indur village |
200000 |
199679 |
completed |
| 15 |
Harur |
Ellapudayampatty |
New G.I Pipeline erection Work at Kammalapatty Purakkal kuttai – Ellapudayampatty Village |
83000 |
0 |
Cancelled |
| 16 |
Harur |
Ellapudayampatty |
New G.I Pipe Line Erection Work at kammalapatty – Ellapudyampatty Village |
125000 |
0 |
Cancelled |
| 17 |
Pappireddypatty |
Madathahalli |
New Pipeline Erection Wrok at Madathahalli SC Street around 1500 Mts Length – Madathahalli Village |
600000 |
0 |
Cancelled |
| 18 |
Pappireddypatty |
Ramiyanahalli |
New G.I Pipe line erection from Existing Borewell near Chekkan Erikarai at Vasudeven Rice Mill – Ramiyanahalli Village |
205000 |
0 |
Cancelled |
| 19 |
Harur |
Polayamballi |
Erection of Group tapping work at Jadayampatty – Polayampalli Village |
30000 |
0 |
Cancelled |
| 20 |
Dharmapuri |
Chettikarai |
COVID – 19 quarantine Campus-500 LPH RO Plant Materials for Government Engineering College, Chetikarai 1st Floor Boys -1 |
349999 |
349999 |
Completed |
| 21 |
Dharmapuri |
Chettikarai |
COVID – 19 quarantine Campus-500 LPH RO Plant Materials for Government Engineering College, Chetikarai 2nd Floor Boys-1 |
349999 |
349999 |
Completed |
| 22 |
Dharmapuri |
Chettikarai |
COVID – 19 quarantine Campus-500 LPH RO Plant Materials for Government Engineering College, Chetikarai 3rd Floor Boys-1 |
349999 |
349999 |
Completed |
| 23 |
Dharmapuri |
Chettikarai |
COVID – 19 quarantine Campus-500 LPH RO Plant Materials for Government Engineering College, Chetikarai 1st Floor girls-1 |
349999 |
349999 |
Completed |
| 24 |
Dharmapuri |
Chettikarai |
COVID – 19 quarantine Campus-500 LPH RO Plant Materials for Government Engineering College, Chetikarai 2nd Floor girls-1 |
349999 |
349999 |
Completed |
| 25 |
Dharmapuri |
Chettikarai |
COVID – 19 quarantine Campus-500 LPH RO Plant Materials for Government Engineering College, Chetikarai 3rd Floor Boys-1 |
349999 |
349999 |
Completed |
| 26 |
Nallampalli |
Kammampatty |
Fixation of Electric Motor in Malayoor Open well and laying of pipeline from open well to Malaiyoor kadu OHT for Water Hydration |
500000 |
499146 |
Completed |
| 27 |
Nallampalli |
Nagarkoodal |
Laying of Pipeline from Kumbalapadi OHT to Muniyappan Kottai and Kattuvalavu for supplying Drinking water |
500000 |
499392 |
Completed |